Scheduled tasks: export/backup import/restore ability is missing
Have just built a Lion system volume from scratch and am in the
process of adding 'third party' applications, such as CCC.
I notice no means/mechanism for copying/transferring the Scheduled
Tasks from 'old' to 'new' system volume.
Considering the tedious nature of creating a Scheduled Task for
'cloning' a single sub-folder (and exclude all other folders),
the addition of a feature to CCC to facilitate the exporting and
importing of Scheduled Tasks would be appreciated.
Comments are currently closed for this discussion. You can start a new one.
Support Staff 2 Posted by Mike Bombich on 07 May, 2012 01:51 PM
CCC's volume identification procedures are generally too restrictive to make this practical. Your source volume, for example, has a new unique identifier, so CCC would refuse to use that volume as the source to a task that was configured with a different source volume. I'm working towards task configurations that will be flexible enough to allow you to re-identify the source and destination volumes, and when I get there, this kind of functionality will be more practical. I'll reconsider adding this functionality then.
Thanks for the suggestion,
Mike
Mike Bombich closed this discussion on 25 May, 2012 09:14 PM.